Effectiveness Evaluation

It allows you to follow up the production effectiveness (productivity).

Important:

The effectiveness evaluation considers that the shorter the actual lead time, the better is the effectiveness in analysis of units. The production amount is also proportional to the effectiveness as well. The higher the production, the better is the evaluation.

Main Fields/Controls

See below the main fields/controls of the effectiveness evaluation:

Scheduled Hours
Production Area
Work Center
Machine

 

For more information on the fields, refer to the topic Terms and Concepts.

Procedures

Viewing the effectiveness evaluation:

1. In Effectiveness Evaluation, click View.

2. Choose the chart option: Operation, Item, Cycle, Tool, Daily or Weekly.

3. View information.