Business Rules
Business rule considered on the production report:
Code |
Description |
||||||||
RN001 |
The time overlap in the report is allowed only if the machine parameterization defines so. |
||||||||
RN003 |
The repeated report, that is, report by item only, is not allowed because it does not have operations. |
||||||||
RN004 |
The amount approved indicates that the item generated in the process was considered good for the next process (operation, inventory, QC). The reworked amount is part of the approved amount as well. |
||||||||
RN005 |
The amount scrapped indicates that the item generated in the process was considered bad to go to the next process and must be taken to the scrap warehouse. |
||||||||
RN006 |
The production can only be reported in hours (zeroed amount). |
||||||||
RN009 |
The production can only be reported for production orders coming from the ERP software. |
||||||||
RN010 |
The progress percentage is updated for the operation directly in the ERP software when it receives the report information via integration. |
||||||||
RN014 |
Reports and reversals must be confirmed in the Legacy database. |
||||||||
RN015 |
The sum of scrap amount of each reason must be the same as the amount scrapped in the report. |
||||||||
RN016 |
The sum of rework amount of each reason must be the same as the amount reworked in the report. |
||||||||
RN017 |
When making reports (stop or production), the corresponding labor reports must be created by Operator or Team, according to definition in the Work Center. |
||||||||
RN018 |
When reporting Overhead Costs and DL (Direct Labor), the hours are suggested and can be edited when the report is defined as Actual. |
||||||||
RN019 |
Splits can be reported from any machine, as long as it is from the same work center of the operation. |
||||||||
RN020 |
Reports are only allowed if there are valid calendar and cycle for the period informed. |
||||||||
RN021 |
When the report type is Production Order, an operation can be reported only if its Work Center is selected as Reported. |
||||||||
RN022 |
When the machine requires setup, it must be informed only in the first production report of the split (split status must be Released). |
||||||||
RN023 |
A setup stop in a machine which requires setup can only be started if it is ended with the production report. |
||||||||
RN102 |
Present the parameter reported in the Work Center Unit only when integrated with Datasul legacy. |
||||||||
RN103 |
When the reported parameter is checked in the Work Center Unit and the manufacturing order report type is per order, it should require the operations linked to this Work Center Unit are recorded. |
||||||||
RN107 |
Create parameter to indicate the Balance in the Split, consider only Qty. Approved, instead of Reported. |
||||||||
RN108 |
Create parameter to automatize the Split closing, when the quantity is greater or equal to the expected one (notice the Balance Parameter in the Split and the Operation Balance “MV_SFCQTS = False”). |
||||||||
RN109 |
Only ask if you want to finish the Operation when the operation total quantity has already been performed and the Parameter “MV_SFCQTS = False”, and leave the default button as “No”. |
||||||||
RN110 |
During the production report, you should notice if the Processor Type is multiple processes or batch to allow report overlap in the same machine. Also notice the number of simultaneous operations and operation number in the machine available. There follow the processor types available:
|
||||||||
RN111 |
Fill out the tool code instead of Resource ID in the browse. Likewise the operator type resource. |
||||||||
RN112 |
When the Work Center Unit is checked as Report DL different from 'do not report', it must require the resource filling out (operator or team). Dispatch list too. |
||||||||
RN113 |
Fill out information about Order/Operation/Split in the messages for better identify what needs to be corrected. As it is a split list, we do not know where there is a problem. |