Production Reports

These are the main measurements of production reports in the production management:

Number of Reports

Counter of reports.

Standard Setup Time

Sum of all setup standard times. For this indicator, you can define the parameter Setup Standard Time as By Operation or By Operation Split.

By Operation - only one standard setup time is considered per operation, regardless of the number of splits and setups.
By Operation Split - one standard setup time is considered for each operation split.
Standard Operating Time

Sum of all standard operating times (labor time or machine time, according to the parameter selected in Processor Type).

Manual - Labor Time.
Single processing - Machine Time.
Batch processing - Machine Time.
Multiprocessing - Machine Time.
Actual Setup Time

Sum of all setup times.

Actual Operating Time

Sum of all operating times.

Regular Hours

Sum of all operating times performed in regular hours of cycle operations.

Regular Hours = Sum of Operating Time - Sum of Extra Time

Extra Hours

Sum of all operating times performed in extra hours of cycle operations.

Quality %

Represents the ratio between amounts scrapped and amounts reported.

Quality = ((Sum of Amounts Reported - Amounts Scrapped) / (Sum of Amounts Reported)) * 100

In other words: Quality = Amount Approved / Amount Produced

Actual Quality %

Actual quality rate. This is not about the quality rate when the product leaves the factory, but the quality of processes, not considering the rework from defective products.

Effectiveness %

It represents the ratio between the standard operating time and the sum of actual operating time. You can even consider the scrap factor to determine the effectiveness.

Effectiveness = Sum of Standard Operating Time / Sum of Operating Time * 100

If the parameter Setup Changes Effectiveness is selected, the setup time must be considered:

Effectiveness = (Sum of Standard Operating Time + Standard Setup Time) / (Sum of Operating Time + Setup Time) * 100

Considering the Scrap factor - Quality:

Effectiveness = Sum of Standard Operating Time / Sum of Operating Time * 100 * Quality