Stop
Main stop measurements of the production management:
| • | Number of Stops |
Total number of performed stops, either Scheduled or Unscheduled.
Important: When a scheduled stop is performed, the system considers it as a single stop. |
| • | Number of Scheduled Stops |
Sum of all scheduled stops which were only scheduled and not performed.
| • | Number of Stops Scheduled and Performed |
Sum of all scheduled which were both scheduled and performed.
| • | Number of Unscheduled Stops |
Sum of all unscheduled stops (corrections, lack of material, etc.).
| • | Scheduled Hours |
Sum of all scheduled hours (no matter if worked or not), considering both hours scheduled during the regular work shift and outside it.
Scheduled Hours = Scheduled Regular Time + Scheduled Extra Time
| • | Unscheduled Hours |
Sum of regular hours and extra hours of unscheduled stops. (Actual time spent)
Unscheduled Stops = Working Time + Extra Time of unscheduled stops.
| • | Total Stop Time |
Sum of working time and extra time of all stops performed (scheduled or not).
Important: The sum of Scheduled Hours and Unscheduled Hours will not be the same as the Total Stop Time, since the scheduled hours may be different from the actual stop time. |
| • | Scheduled % |
Percentage variance between actual time and scheduled time of all scheduled stops.
Scheduled % = Total Scheduled Time / Total Actual Time (of scheduled stops only).
Example:
Scheduled Stop Time: 10 hours
Actual Stop Time: 12 hours
Scheduled %: 120%
| • | Unscheduled % |
Percentage variance between the total time of unscheduled stops and the total time of stops.
Unscheduled % = Total Time of Unscheduled Stops / Total Time of Stops